Zulu Marine Construction will be completing required cleaning/repairs of the stormwater retention system in Pine Ridge next week (January 12 – 17).
This is required work to comply with the Town of Bluffton stormwater management requirements.
Please be aware of the workers in your location. In some cases, it may be necessary for workers to access the lagoons through some private properties.
Below is the proposed schedule and map location(s) of work.
Project: Pine Ridge Development – Pond Maintenance Location: Bluffton, South Carolina Contractor: Zulu Marine Schedule Year: 2026
Phase 1 – Mechanical & Vegetative Debris Removal
Date
Location
Planned Activities
01/12/2026
Pond 1-behind 106 – 120 Holly Ridge
Woody debris removal, tree trimming, mechanical aquatic debris extraction
01/13/2026
Pond 1B -behind 113 – 121 Holly Ridge
Woody debris removal, tree trimming, mechanical aquatic debris extraction
01/14/2026
Pond 3 – behind 1 – 11 Woodland Hills and behind 102 – 108 Pine Ridge Dr.
Woody debris removal, tree trimming, mechanical aquatic debris extraction
01/15/2026
Pond 4 – behind 71 -103 Pine Ridge Drive and behind 36 – 42 Heather Glenn and behind 3 – 4 Stonefield Lane
Woody debris removal, tree trimming, mechanical aquatic debris extraction
01/16/2026
Pond 7 – behind 12 – 22 Grove Way
Woody debris removal, tree trimming, mechanical aquatic debris extraction
01/17/2026
Ponds 8 & 9 – pond 8 backs up to 8 -20 on Pine Ridge, 8 -23 Torrey Lane and 11 -17 Wiregrass Way and 3-9 Boxtail Cres. Pond 9 backs up to 2-12 Spruce Drive.
Woody debris removal, tree trimming, mechanical aquatic debris extraction
Phase 2 – Chemical Treatment
Date
Ponds
Planned Activities
01/19/2026
Ponds 1, 1B, 2 – pond 2 backs up to 25-29 Woodland Hills Drive and 4-6 Holly Ridge.
Chemical treatment of aquatic vegetation
01/20/2026
Ponds 5, 6, 10 – pond five backs up to 6-10 Longleaf Court and 45 -60 Pine Ridge Drive. Pond 6 backs up to 3-35 Pine Ridge Drive and 5 Bristlestone Court. Pond 10 backs up to 15-27 Spruce Drive and 4-40 Wiregrass Way.
Chemical treatment of aquatic vegetation
General Notes
– Work will be conducted during normal daytime operating hours unless otherwise approved. – Schedule subject to weather conditions and site access. – All debris will be disposed of in accordance with local and environmental regulations. – Chemical treatments will comply with all applicable state and federal guidelines.